Tuesday, December 6, 2022

Driveway Remodel Part 4

Pour Day! Any concrete pour is a team effort, and my contribution was to set my alarm for 6:00 am (!) and be ready to open the garage door. The pour begins with a truck which carries up to nine cubic yards of concrete. I've been wondering if this is the source of the phrase "the whole nine yards" ?  The truck dispensers the specified mix into a hopper which is connected to a high powered concrete pump which is parked behind the truck (yellow thing in the photo).


The pump dispenses concrete from a four inch diameter feed pipe - the pump and pipe requires a two man crew. 


Another crew member with a spade follows the pump - the spade is used to push down and agitate the fresh concrete which releases any air pockets.


The first step in finishing is known as "rodding" and this begins as soon as a sizeable section of concrete has been pumped into the driveway. Two crew members work the surface with a straight 2" x 4" to establish a mostly level surface at the desired grade. Pumping concrete continues unabated in the adjacent area.


After rodding, the concrete is worked over with a four foot wooden bull float which is the first step in establishing a flat surface - the bull float works out the high spots and helps identify any low points.


Control joints are established early n the process.


This is later after the second concrete truck has arrived and rodding of the "phase #2" section is underway:


As the pour continues up the driveway, hand finishing of the first section begins:



Control joints are established initially with a string line. The crew have a variety of extension poles which can be used to access areas that are otherwise out of reach. It the photo below a string line is tied to a pole in order to snap a faint line....


...which can be followed by the jointing tool:


A two-foot bull float is used to smooth out the surface after jointing:


By now the third truck is dispensing the final section of the driveway:


At the same time, the first section is being hand finished for the second time:


The final step is a broom finish: 50% horse hair, 50% nylon, which provides a non-slip surface:


This process continues through each section of the pour...




All done!


Pour day plus five - we have been watering the concrete am and pm every day; this is important to slow the curing which helps prevent cracking in areas beyond the control joints. 


Pour day plus seven - the driveway is open for business! We will be watering the concrete at least nce a day for another week; full curing tales 28 days.

To be continued...

Wednesday, November 23, 2022

Driveway Remodel Part 3

As mentioned in Part 2, the driveway remodel has had some issues with the weather. However, this was the sky the night before the plastic sheeting was removed from the wall. I'm writing almost two weeks hence, and it has not rained since.

This is how the wall looks about a week after it was poured:


By this time the blocking and the forms have been removed from the rear side of the wall and it is time to backfill.  


The landscape fabric goes in first...


This is followed by drainage rock, the perforated drainage pipe, and more drainage rock. 

This is the last photo of the original driveway, taken right before I left for work:

By the time I got back, the concrete was gone, the juniper had been ripped out and the first load of road base had been spread:


This is later after most of the road base has been spread out.


The road base is then heavily watered and partially compacted with the Bobcat.


Its difficult to see in the next photo, but string lines have been set left-to-right across the driveway. This helps to identify low or high points in the road base.  Any such areas are marked with spray paint and modified accordingly.


The final step is running a compactor over the entire area which provides a very solid base for the concrete:


The next step is to install the drainage system in front of the garage. The old drain was just a channel in the concrete that never worked property; the front of the garage would flood under the slightest provocation.


The new drain consists of one (1) meter long precast sections which are designed to lock together and provide a consistent 2% slope towards the preexisting subsurface drain. The sections are set on concrete piles. Doing this ahead of the main pour ensures a precise position. Cast iron grilles will be installed later.


A few days later and the rebar has been installed at two foot centers; at this point the rebar is laid on top of the road base. 


We ripped up the juniper but the trees next to the garage have been given a reprieve. 


The new concrete will extend to the path at the front of the left side gate. The concrete path beyond the gate and the concrete patio in the backyard will be replaced later, with anything but concrete!


The final preparations before the pour include installing a foam strip at the junction between the wall and the driveway - this is just about visible as the black ribbon in the photo below:


The rebar is lifted onto two inch dobies (small concrete blocks) at the last minute - once lifted, the rebar presents a serious trip hazard.


To be continued...

Wednesday, November 9, 2022

Driveway Remodel Part 2

More progress on the driveway! This is the scene on the morning of Day 8, after two days of rain which has turned the whole yard into a mud slide.


There is about a foot of standing water in the bottom of the footing. It carried on raining on and off during the day, but not enough to stop work completely


 By mid-afternoon the blocking behind the wall was complete...


And at the end of the day the electrician came by to install the conduit which will go inside the wall and the recessed boxes for the lights. You can just about see this in the next photo, parallel to the rebar:


The next day the weather was nice enough to complete the driveway side of the form and install the blocking at that side.


Then it was a case of rain rain, and more rain....for the next three days...


We had our pour scheduled for first thing Monday. It was a bit nerve wracking on Sunday when it was still tipping it down with rain, but in the event it was dry when it mattered. 

The crew started rigging up at 6:00 am when it was still dark, and the first concrete truck pitched up at 7:00 am. The process starts with pumping concrete into the base of the footing and works up hill. 




Then it is on to the wall. ..


All the concrete was poured by 9:00 am. It took three trucks and twenty four (24) cubic yards of concrete to pour the footing and the wall. Time fort cuppa tea.


The finishing process starts as soon as the last concrete truck leaves. Stripping the forms on the day of the pour enables the wall to be finished to a much higher quality, but is fraught with danger: strip too soon and the concrete will fail!  Not many contractors would strip a wall this size on the day of the pour, but the guys from Veteran's Concrete don't take any prisoners!


The excess concrete is cleaned off the forms; some of the lumber will be reused for the driveway and entrance path.


The next photo shows the contrast between the finished section of the wall and the upper section which has just been stripped:


There was just enough time to finish the face of the wall and construct a basic structure to support some plastic sheeting...


Before the heavens re-opened:



Now there is a footing below the standing water:


To be continued.....